Pacific Northwest Hydrogen Hub (PNWH2) Environmental Impact Statement
Virtual Public Information Forum
Project Milestone Schedule
The milestone schedule below reflects key dates in the National Environmental Policy Act (NEPA) process. Exact dates are subject to change.
Notice of Intent (NOI) published to Federal Register: December 18, 2024
Public Scoping Period: December 18, 2024 — March 3, 2025
Virtual Public Scoping Meeting: January 22, 2025
In-Person Public Scoping Meetings: February 11 and February 13, 2025
Analyze scoping comments and prepare Environmental Impact Statement (EIS): January 2025 — August 2025
Public Scoping Report Published to Public Website: April 2025
Issuance of Draft EIS: August 2025
Public comment period for the Draft EIS: August 2025 — October 2025
Issuance of Final EIS: April 2026
Issuance of Record of Decision: May 2026